Grain Systems PNEG-300 User Manual

Installation of roof mounted level switches, Instructions, Rotary switch instructions

Advertising
background image

Date: 12-16-10

Instructions

1004 East Illinois Street • Assumption, IL 62510 • 1-217-226-4421

Page 1 of 4

Printed in the U.S.A.
Copyright © 2010 by GSI Group
www.gsiag.com

PNEG-300

PNEG-300

Rotary Switch Instructions

Installation of Roof Mounted Level Switches

Drill 2" diameter holes through roof panels at locations shown on

Page 3

. Use a mounting plate as a

pattern and drill four (4) 3/8" holes through roof panels at each switch location so the plate can be bolted to
the roof.

Attach flex-coupling to the power-pak. Apply teflon tape or pipe sealant (not included) to power-pak pipe
threads and thread power-pak into mounting plate coupling. Conduit opening in power-pak should be at
right angles to roof rib or face toward eave.

Caulk underside of mounting plate above and both sides of 2" hole. Bolt to roof panel.

Attach shaft extension according to

Figure 2

and Figure 3 on Page 2

. Use teflon tape or pipe sealant

(not included) on shaft guard (see

Figure 2

and Figure 3 on Page 2

for lengths) and thread to underside

of mount plate coupling. Add 1/4" drilled coupling and paddle. (NOTE: Single vane paddle is used on LOW
level switch.
)

Figure 1 Overflow Rotary Switch Assembly

Advertising