Attaching the roof panels, Chapter 7: roof assembly – Grain Systems Tanks PNEG-4060A User Manual

Page 110

Advertising
background image

Chapter 7: Roof Assembly

Figure 7-26 Exploded view of a 6–hole intermediate purlin

A

Purlin

D

Left Purlin clip (CTR-0489)

B

Right Purlin clip (CTR-0490)

E

A-frame roof assembly

C

7/16 x 1-1/4 in. flange bolt (S-10250)

F

7/16 in. flange nut (S-10251)

NOTE: Purlin part numbers will vary with location.

After You Finish
Repeat this procedure for the remaining 6–hole intermediate purlins of the roof assembly.

Attaching the Roof Panels

Roof panels overlap the previous roof panel, giving protection from outside elements.

Before You Begin

Ensure all A-frame roof rafter assemblies are installed, and ensure all intermediate purlins are installed
and properly tightened. Predetermine the manway access location.

What You Should Know

For adjustment purposes, roof panels will be installed to each rafter first, causing exposed gaps between
each roof panel group (see figure below). After all roof panels are installed, ensure that all installed hard-
ware (flange bolts with sealing washers and flange nuts) are tightened to secure the roof panels.

110

Pneg-4060A 60 Ft Diameter 40-Series Bin