6. To remove the phase barriers on each phase,
push the moving contact assembly and the
adjustment screw toward the rear of the breaker,
then pull the phase barrier up and to the front, as
shown in Figure 8.
7. Remove the retaining clip from the center
mounting post of each line and load draw-out
primary contact finger assembly, as shown in
Figure 9, then remove the fingers. Be sure to save
the existing flat washer from each assembly for
reuse, but discard the retaining clip.
8. Remove the four hex-head bolts securing the
pole assembly to the breaker, as shown in Figure
10. Tilt the pole assembly forward and lift
upward to remove it from the breaker. Be sure to
save all hardware.
CAUTION: The pole assembly is heavy and awk-
ward. Take care not to damage the assembly or the
breaker’s common trip shaft while removing the
pole assembly.
Figure 8. Removing the phase barriers.
Figure 9. Removing the draw-out primary contact fingers.