3.7.3 Battery over current protection and wire sizing

NOTE !

Please read the safety precautions at the front of this guide carefully, and

thoroughly review the battery manufacturers installation and maintenance
manual before connecting the batteries to the UPS.

The remote rack mounted batteries are to be used then DC over current

protection must be provided by others.

Choose an appropriate DC fuse or circuit breaker using the current data in the

chart below.

Minimum battery cable requirement is based on the current data below.
The maximum available fault current from the battery supply is: 20kA.
The minimum breaker voltage rating is 540V.

The AC values below are current ratings per phase.

These maximum and nominal ratings should be considered when choosing the appropriate AC

over current protection device.

NEC (National Electric Code) Section 210-20 a rules must be applied.

DC current rating is the nominal battery discharge current which the UPS allows.

(See Fig. 3.7.1-1 and 3.7.1.2)

AC Input Rectifier

AC Input

AC Input

Bypass

DC Input

F1

F3

UPS rating

Nom. Max.

F2

Nom. Max.

F4

SG Series 225

338 A

380 A

271 A

338 A

380 A

444 A

SG Series 300

451 A

490 A

361 A

451 A

490 A

592 A

Size of Branch Circuit Over current Protection - All Models: - "CAUTION - To reduce the risk of fire,

only connect UPS to a circuit provided with (See below) maximum amperes branch circuit over

current protection in accordance with the NEC (National Electric Code), NSI / NFPA 70

AC Input Rectifier

AC Input Bypass

AC Input

DC Input

UPS rating

F1

F2

F3

F4

SG Series 225

450 A

350 A

450 A

600 A

SG Series 300

600 A

500 A

600 A

700 A

WIRING
Wire sizing according to
NEC Section 210-20 (a) Table 310-16
Use 75°C (167°F) copper wire

Wiring requirements:
AC INPUT RECTIFIER:

3-Phase, 3 wire plus Ground

AC INPUT BYPASS:

3-Phase, 4 wire plus Ground

AC OUTPUT:

3-Phase, 4 wire plus Ground

DC INPUT:

2 wire (positive and negative) plus Ground

Maximum cable diameter that terminals can accept

Refer to torque specifications table for torque requirements

UPS rating

Rectifier Input

Bypass Input

DC Input

AC Output

GND

SG Series 225

2 x 500 kcmil

2 x 500 kcmil

2 x 750 kcmil

2 x 500 kcmil

350 kcmil

SG Series 300

2 x 750 kcmil

2 x 500 kcmil

2 x 750 kcmil

2 x 500 kcmil

350 kcmil

Modifications reserved

Page 19/40

OPM_SGS_ISG_M22_M30_2US_V010.doc

Installation Guide SG Series 225 & 300 UL S2