GE Industrial Solutions 664 Infinity C DC to DC Power System User Manual
Page 8
663 / 664E Installation Guide
CC848921016 r02 December 2012
Page 8
Step 4
Run and Terminate Alarm Cabling
• Run and terminate alarm cabling
• Jumper settings are available for both
Close on Alarm and Open on Alarm
extensions
• Verify alarm extensions with the Alarm
Center
• See Pulsar Edge Controller Family
Product Manual for additional information
Step 5
Run & Term. Supply and Return Cables
Output cabling
• With GMT fuses and circuit breakers
removed, land all supply and return cabling
at the rear of the system
• Circuit breaker lug landings -
1/4” on 5/8 inch centers
Torque to 240 in-lb
• GMT wire landings –
Strip wire 3/8”
Torque to 13 in-lb
Connectorized
Alarm Cable
connection
Front
Circuit breaker
landing positions
GMT
landing positions