Xylem AC2008B Series HSC3 Base Mounted Centrifugal Pump User Manual

Page 6

Advertising
background image

6

Foundation bolts should be set in concrete as shown in

Illustration 3. An optional 4-inch long tube around the bolts at

the top of the concrete will allow some flexibility in bolt align-

ment to match the holes in the base plate. Allow enough bolt

length for grout, shims, lower base plate flange, nuts and

washers. The foundation should be allowed to cure for several

days before the base plate is shimmed and grouted.

8. Base Plate Setting (Before Piping)
NOTE: This procedure assumes that a concrete foundation

has been prepared with anchor or hold down bolts extending

up ready to receive unit. It must be understood that pump and

motor have been mounted and rough aligned at the factory. If

motor is to be field mounted, consult factory for recommenda-

tions. Bell & Gossett cannot assume responsibility for final

alignment.

a. Use blocks and shims under base for support at anchor

bolts and midway between bolts, to position base

approximately 1" above the concrete foundation, with studs

extending through holes in the base plate.

b. By adding or removing shims under the base, level and

plumb the pump shaft and flanges.

c. Draw anchor nuts tight against base, and observe pump

and motor shafts or coupling hubs for alignment. (Tem-

porarily remove coupling guard for checking alignment.)

d. If alignment needs improvement, add shims or wedges at

appropriate positions under base, so that retightening of

anchor nuts will shift shafts into closer alignment. Repeat

this procedure until a reasonable alignment is reached.
NOTE: Reasonable alignment is defined as that which is

mutually agree upon by pump contractor and the accepting

facility (final operator). Final alignment procedures are cov-

ered under “Alignment Procedures.”

e. Check to make sure the piping can be aligned to the pump

flanges without placing pipe strain on either flange.

f. Grout in base plate completely (See “Grouting Procedure”)

and allow grout to dry thoroughly before attaching piping to

pump. (24 hours is sufficient time with approved grouting

procedure.)

9. Grouting Procedure
Grout compensates for uneven foundation, distributes weight

of unit, and prevents shifting. Use an approved, non-shrinking

grout, after setting and leveling unit. (See Illustration 4)
a. Build strong form around the foundation to contain grout.
b. Soak top of concrete foundation thoroughly, then remove

surface water.

c. Base plate should be completely filled with grout.
d. After the grout has thoroughly hardened, check the founda-

tion bolts and tighten if necessary.

e. Check the alignment after the foundation bolts are

tightened.

f. Approximately 14 days after the grout has been poured or

when the grout has thoroughly dried, apply an oil base paint

to the exposed edges of the grout to prevent air and mois-

ture from coming in contact with the grout.

10. See ANSI/OSHA Coupler Guard Removal/Installation

(next page)

11. Alignment Procedure
NOTE:
A flexible coupling will only compensate for small

amounts of misalignment. Permissible misalignment will vary

with the make of coupling. Consult coupling manufacturer’s

data when in doubt.
Allowances are to be made for thermal expansion during cold

alignment, so that the coupling will be aligned at operating

temperature. In all cases, a coupling must be in alignment for

continuous operation. Even though the coupling may be lubri-

cated, misalignment causes excessive wear, vibration, and

bearing loads that result in premature bearing failure and

ultimate seizing of the pump. Misalignment can be angular,

parallel, or a combination of these, and in the horizontal and

vertical planes. Final alignment should be made by moving

and shimming the motor on the base plate, until the coupling

hubs are within the recommended tolerances measured in

total run-out. All measurements should be taken with the

pump and motor foot bolts tightened. The shaft of sleeve

bearing motors should be in the center of its mechanical float.
NOTE: Proper alignment is essential for correct pump opera-

tion. This should be performed after base plate has been

properly set and grout has dried thoroughly according to

instructions. Final alignment should be made by shimming

driver only. Alignment should be made at operating

temperatures.

Illustration 3 – Foundation

Illustration 4 – Setting Base Plate and Grouting

WARNING: Unexpected Start-up Hazard

Disconnect and lock out power before servicing.

Failure to follow these instructions could result in serious

personal injury or death and property damage.

PIPE

SLEEVE

FOUNDATION

BOLT

BUILT-UP

CONCRETE FOUNDATION

GROUT ONLY TO

TOP OF BASE RAIL.

PUMP

BASE RAIL

APPROX.

1" GAP

CONCRETE

FOUNDATION

LEVELING OF PUMP BASE

ON CONCRETE FOUNDATION.

GROUT

WASHER

ALLOW 1" FOR SHIMS.

PLACE ON BOTH SIDES

OF ANCHOR BOLTS.

NOTE:

TO KEEP SHIMS IN

PLACE ALLOW GROUT

TO FLOW AROUND

HOLD DOWN LUGS.

(OPTIONAL)