Pump station startup

Confirm the job site voltage

1. Check these items before you apply power or close the disconnect:

a) Check all of the power wiring connections and secure them as required.
b) Confirm with the owner/installing contractor if there are plans for any required

building automation or remote connections.

c) Inspect and/or install any customer remote terminations.

2. Make note of the design data supplied on the data label. The label is located on the

inside of the control panel door.

3. Use a volt meter to check the voltage on the incoming power terminals at the

disconnect.

4. Compare the voltage to the data on the nameplate.

Connect the storage tank

DANGER:
Explosion hazard. Prevent tank explosion. Do not install the tank when the system shut-off
pressure exceeds the tank pressure rating.

DANGER:
Explosion hazard. Prevent tank explosion. Install a pressure relief valve on the tank inlet
with a set point no greater than tank rating.

1. Precharge the storage tank before you connect it to the system.

The air precharge needs to be 5 to 10 psi less than the system operating pressure.

2. If the storage tank has already been installed and not precharged, then disconnect the

system piping from the tank and equalize it to atmospheric pressure. If an isolation
valve and drain are provided, then use them.

3. Apply air pressure to the tank through the air charging valve and pressurize to field

conditions.
This needs to be equal to the NFSD restart pressure of 5 to 10 psi below the operating
pressure.

4. Reconnect the tank to the system piping. Tank should be installed on the discharge

side of the system.

Check for available suction water

1. Open all supply, discharge, and pump isolation valves. Also open any other package

valves.

2. Close the bypass valve if it is installed in the piping by others.
3. Inspect the capillary tubing from the pump discharge to the suction header:

a) Open the petcocks that feed the tubing.
b) Make sure that the plastic tubing does not touch any metal surface. Protect the

tubing with insulation in order to prevent abrasion where it can possibly touch
metal.

4. Open a faucet in order to create a demand for water on the system pressure piping.
5. Observe the suction pressure and confirm that it is equal to or greater than the suction

pressure listed on the nameplate. System is designed for a specific suction pressure.
Deviation results in degraded system performance. Contact factory if suction pressure
varies from design specifications.