3. Remove coupling guard if provided. Attach a sling

to the lifting lugs on the side of the discharge head

through windows and hoist discharge head over the

protruding top shaft (or stub shaft).

Do not bump or scrape the shaft

protruding above the column. This could

result in bending or damaging the shaft.

4. Orient the discharge head in the required position

and lower the head. Centering the vertical hole with

the top shaft protruding above the column. For

threaded column, continue to lower the discharge

head until the large threaded hole in the bottom

of the discharge head rests squarely on top of

column. Clean the threads at upper end of column

assembly and lubricate with thread compound.

Rotate discharge head, screw it onto the column,

for short set-pump, (without the column adjusting

nipple) butting the top of column tightly against the

discharge head.

5. If pump has a column adjusting nipple (631), for

open lineshaft, screw the discharge head onto the

column nipple until the end of the stub shaft is

“HT” below the face the driver mounting flange

of the discharge head. (See Figure 7 for detail.)

For enclosed lineshaft, screw the discharge head

onto the column nipple until the “F” dimension is

satisfied (See Figure 7). Tighten the lock ring (639).

6. For flanged column, continue to lower the discharge

head until the discharge head engages the column.

Install capscrews and secure discharge head to the

column flange. Tighten capscrews gradually in

diametrically opposite pairs. Lift pump assembly

high enough to allow rotation of the supports.

Realign and lower assembly. Install and tighten

remaining capscrews. Repeat the rotating and

the tightening procedure until all capscrews are

uniformly tight.

7. Hoist the discharge head by lifting lug and remove

the elevator clamp attached to column.

8. Remove the support timbers or I-beams and clean

the top of foundation or base plate. Orient the

discharge head in the required position.

NOTE: Sling should be rated to handle in excess of the

pump weight.

9. Lower bowl, column and head assembly, until

discharge head mounting flange engages base plate.

Secure discharge head to the foundation or base

plate. Check the levelness of the discharge head in

all directions, utilizing a machinist level across the

driver’s mounting surface of the discharge head.

10. Check whether the top shaft (or stub shaft) is in

the center of the stuffing box bore. If not, the shaft

must be centered by shimming the head base and

the sub base (or the foundation).

11. Rotate the shaft approximately 90 degree. Check

again whether the shaft is at the center of the

stuffing box bore or not. If not, either the top

shaft is bent or the first shaft below it did not butt

properly. Correction must be made before the

installation procedures can proceeds.

INSTALLING THE STUFFING BoX
Assemble stuffing box as shown in Figure 8.

1. Clean the surface of the discharge head where

the stuffing box will be mounted and remove any

nicks or burrs with a fine flat file. Position gasket

on surface. Slide stuffing box (616) down over

headshaft and into position on the gasket. Secure

stuffing box with capscrews.

2. Grease the packing ring (620) for easier installation.

3. Twist the packing ring sideways to get it around the

shaft easily. Start the first ring into the stuffing box.

When the entire ring is worked in using the fingers,

tamp it down using a split wood bushing (or equal)

and push the packing ring down firmly. It must seal

on the shaft and bore of the stuffing box. Install

three (3) rings in this manner. Stagger ring joints

90 degrees apart. The split gland may be used as a

tamper for the top ring.

4. Insert lantern ring (622) into stuffing box. Be sure

it is properly positioned so that it aligns with the

lubrication passage in the stuffing box.

5. Insert three (3) additional rings of packing. Stagger

ring joints 90 degrees apart.

CAUTION

L

STUB SHAFT

J

M

TUBE NIPPLE

C

STD

LINESHAFT

18.00

COL. NIPPLE

H

D

E

HT

F

HEAD SHAFT

CD

XH

Figure 8

Shaft Size (in.)

1.00

1.19 1.50 1.69 1.94 2.18 2.44

Head Size HT

M

4"

2.50 17.50 H = 5.88 F = 17.62

6"

2.88 17.50 H = 6.25 F = 17.25 H = 5.63 F = 17.88

8"

3.00 17.50 H = 7.38 F = 16.13 H = 6.75 F = 16.75 H = 6.25 F = 17.25

10"

3.00 17.50 H = 7.63 F = 15.88 H = 7.00 F = 16.50 H = 6.26 F = 17.00

12"

4.69 21.00

H = 9.19 F = 17.18 H = 8.69 F = 18.31