Installation – Xylem MM 414B Series 150E and 157E Low Water Cut-Off/Pump Controllers For Steam Boilers and Other Level Control Applications User Manual

Page 4

Advertising
background image

4

If the control will be the primary low
water fuel cut-off,
size the steam (top)
and water (bottom) equalizing pipe lengths
so that the horizontal cast line on the body
is 1

3

/

8

” (35mm) below the boiler’s normal

water level, but not lower than the
lowest safe permissible water level, as
determined by the boiler manufacturer.

OR

If the control will be the secondary low
water fuel cut-off,
size the steam (top) and
water (bottom) equalizing pipe lengths so
that the horizontal cast line on the body is
at or above, the lowest safe permissible
water level, as determined by the boiler
manufacturer.

STEP 1 - Determine the Elevation at Which the
Low Water Cut-Off/Pump Controller Must be Installed

INSTALLATION –

TOOLS NEEDED:
Two (2) pipe wrenches, one (1) flatblade screw-
driver, and pipe sealing compound.

IMPORTANT: Follow the boiler manufacturer's
instructions along with all applicable codes and
ordinances for piping, blow down valve and water
gauge glass requirements.

1

3

/

8

"

STEAM EQUALIZING PIPE

VERTICAL EQUALIZING PIPE

NORMAL BOILER WATER LINE

AS A PRIMARY
LOW WATER CUT-OFF/PUMP
CONTROLLER

BURNER CUT-OFF LEVEL AT CAST LINE

LOWEST
PERMISSIBLE
WATER LEVEL

(35mm)

WATER

EQUALIZING

PIPE

BLOW DOWN VALVE

BLOW DOWN VALVE

STEAM EQUALIZING PIPE

VERTICAL EQUALIZING PIPE

BLOW DOWN VALVE

BURNER CUT-OFF LEVEL AT CAST LINE

LOWEST
PERMISSIBLE
WATER LEVEL

BURNER OFF

WATER

EQUALIZING

PIPE

AS A SECONDARY
LOW WATER CUT-OFF/PUMP
CONTROLLER

BLOW DOWN VALVE

Advertising