Installation – Xylem MM 214E Series 61 Low Water Cut-Off User Manual

Page 2

Advertising
background image

Gauge Glass Mounted

Directly into Boiler

CUT-OFF
LEVEL

1" BLOW DOWN

VALVE

For Boilers with

Independent Water Columns

1" STEAM

EQUALIZING PIPE

MODEL 61
LOW WATER
CUT-OFF

1" WATER

EQUALIZING PIPE

1" WATER

EQUALIZING PIPE

1" WATER

EQUALIZING PIPE

CUT-OFF
LEVEL

MODEL 61
LOW WATER
CUT-OFF

2

a. Whether the gauge glass is mounted directly into the boiler or on an independent water column, the

cut-off line on the 61 body casting should be mounted 1/2” (15mm) above the lowest visible point of the
gauge glass.

a. Locate the gauge glass and

determine the level that the 61
has to be mounted at in order
to achieve the criteria in Step 1.

b. Pipe the 61 following the

diagrams shown to the right.
Follow the diagram that
represents your boiler.

c. Crosses should be used at

each right angle connection for
inspection and cleaning.

d. Make sure the blow-down

valves are full port.

e. Test the Model 61 before

leaving the site

STEP 2 - Installation of the Model 61

Model 61 – For Steam Boilers with 1” (25mm) Equalizing Lines

INSTALLATION –

TOOLS NEEDED:
One (1) flathead screwdriver and two (2) pipe wrenches.

STEP 1 - Determine the Location of the Low Water Cut-Off

MM-214(C) 9/5/06 9:40 AM Page 3

California Proposition 65 warning! This product contains chemicals known to the

state of California to cause cancer and birth defects or other reproductive harm.

Previous controls should never be installed on a new system. Always install new

controls on a new boiler or system.

CAUTION:

A more frequent replacement interval may be necessary based on the condition of

of installation or two (2) years from the date of manufacture.

Failure to follow this warning could cause property damage, personal inj ury or death.

!

the unit at time of inspection. McDonnell & Miller s warranty is one (1) year from date

&

'