a. The line on the casting of the model 61 must be installed above the lowest permissible water level

determined by the boiler manufacturer.

a. Study the figures to the right and determine which

figure shows how the 61 control will be attached to
the boiler.

Figure 1. Connect the upper equalizing pipe to
the riser going to the radiation or to the compression
tank. Connect the lower equalizing pipe to any
available opening in the side of the boiler. NOTE: If
no opening is available in the side of the boiler,
connect the lower equalizing pipe into the drain
connection.

Figure 2. If there is a tapping available on the
top of the boiler connect the upper equalizing pipe to
it. NOTE: During initial filling or after blow down the
upper equalizing pipe and possibly the 61 control will
have an air pocket. Connect a vent or bleed valve on
the top of the vertical equalizing pipe. If the Test-N-
Check (TC-4) valve is used the vacuum breaker can
be used to bleed the air pocket.
CAUTION: When bleeding an air pocket manually,
protect yourself from being burned with hot water.

Figure 3. If there is no tapping available on the
boiler, connect both the upper and lower equalizing
pipe into the vertical riser going to the radiation or to
the compression tank. IMPORTANT: The horizontal
equalizing pipe should be below the horizontal
run going to the radiation. If it is not, an air pocket
will be created and a vent or bleed will have to
be installed.

b. Test the Model 61 before leaving the site.

NOTE: If no Test-N-Check (TC-4) valves were used,
do this test before filling the system completely.

STEP 2 - Installation of the Model 61

Model 61 – For Hot Water Boilers with 1” (25mm) Equalizing Lines

INSTALLATION –

TOOLS NEEDED:
One (1) flathead screwdriver and two (2) pipe wrenches.

For float type controls it is recommended that Test-N-Check

®

(TC-4) valves be used in the upper and

lower equalizing lines. They offer a functional means for testing the 61 control, and conform to the
ASME CSD-1 code.

STEP 1 - Determine the Location of the Low Water Cut-Off

VERTICAL RISER
TO RADIATION

HOT WATER

BOILER

MODEL

61

VERTICAL RISER TO RADIATION
OR COMPRESSION TANK

HOT WATER
BOILER

TC-4

TC-4

MODEL

61

HOT WATER
BOILER

AVAILABLE OPENING
IN TOP BOILER

AIR
VENT

MODEL

61

Figure 1

Figure 2

Figure 3

MM-214(C) 9/5/06 9:40 AM Page 4