Model lsn, 3 stuffing boxes, 4 lubrication and change of lubricant – Xylem LSNIH User Manual

Page 17: 5 coupling

Advertising
background image

Installation, Operating and Maintenance Instruction

Model LSN


LSN 100-english

page 15

Revision 01

Article No 771076024

Issue

01/2010

If the liquid being handled leaks out at the mechanical
seal, it is damaged and must be replaced.
Replacement of the mech. seal according to
accompanying "Mounting Instructions for Shaft
sealing".

7.3 Stuffing boxes

Stuffing boxes require constant maintenance, see
chapter 6.2 section "Stuffing box". If the leakage rate
can no longer be set correctly, the packing is worn out
and must be replaced in good time (increased wear on
shaft sleeve). Replacement of stuffing boxes acc. to
attached "Mounting Instructions for Shaft Sealing".

Because of the risk of accidents, addition of
packing to pumps during operation or at
operating pressure or temperature is strictly
forbidden!

7.4 Lubrication and Change of Lubricant

7.4.1 Oil lubrication

Temperature at

bearing

First oil change

after .....

operating hours

All further oil

changes

after .....

operating hours

up to 60°C

300

8760 *)

60°C - 80°C

300

4000 *)

80°C - 100°C

200

3000 *)

*) at least 1x year

In plants endangered to explosion the oil
changeing intervals must be kept under any
circumstances!

Oil changing

After the first ....... operating hours, drain oil (oil
drain "GD" with drain plug 903.51) and flush with
fresh oil. Clean oil drain plug and close oil drain
again.

Fill in new oil according to chapter 6.5.

If the pump is left idle for a longer time, the oil
should be changed after two years.

Old oil must be disposed of in accordance with
the valid national environmental regulations.

Oil quality

Name

Lubricating oil

CLP46

DIN 51517 or

HD 20W/20 SAE

Symbol acc. DIN 51502

Kinematic viscosity at 40°C
Flash point (acc. to Cleveland)
Setting point (Pourpoint)
Application temperature *)

46 ±4 mm

2

/s

+175°C

-15°C

higher than

permitted bearing

temperature

*) For ambient temperatures under -10°C an other suitable type of
lubrication oil must be used.
Request required.

Oil quantity

Bearing bracket

Oil quantity in l

24

0,5

32

1,1

42

1,4

48

1,7

7.4.2 Grease lubrication
Re-greasing

Grease lubricated bearings with the possibility of
re-greasing must be re-lubricated all 4000
operating hours, but at least 1x year. Clean
lubricating nipples (636) first.

Quality of grease lubricant ...
... corresponding to NLGI GRADE 2

Quantity of re-greasing (approx. value)

Bearing bracket

bearing at pump

side

bearing at drive

side

24

9g / 10cm

3

14g / 16cm

3

32

13g / 15cm

3

20g / 22cm

3

42

18g / 20cm

3

33g / 35cm

3

48

23g / 26cm

3

42g / 46cm

3

If the pump is left non-operational for a longer
time, the grease in the bearings should be
changed after 2 years.

7.5 Coupling

Check the clearance in the coupling components
regularly approx. every 1000 operating hours, but at
least 1x year, the radial clearance in the coupling parts
must be checked.
For couplings with rubber pads the following applies:
Unless a clearance in the couplings is necessary, the
coupling pads may wear out to approximately ¼ of
their usual thickness, before they have to be changed.
To measure the clearance in the coupling place a
mark on the O.D. of each coupling hub (see following
pic). Then fixing one hub, turn the opposite hub as far
as possible. Then measure the distance (∆S

V

)

between the marks of the coupling. If this measure
exceeds the value given in the chart, the packings
must be replaced. They must be replaced in sets.

Size

80 95 110 125 140 160 180 200 225 250 280 315 350 400

S

v

[mm] 5,0 6,0 7,0 8,0 8,5 8,0 8,0 8,5 9,0 10,0 11,5 10,5 11,5 13,0

If wear is heavy, it must be assumed that the
motor is not properly aligned with the pump or
that the distance between the coupling sections
has changed. Replace worn elements and re-
install or adjust coupling, as described in
chapter 5.3.

Advertising
This manual is related to the following products: