Commissioning and decommissioning
6.2 Decommissioning/
storing
top the machine
a) Switch the machine off.
b) If available close the cut off device in the suction
and pressure pipe.
c) Disconnect the machine from the electricity
source.
d) Depressurise the machine: Open the pipes
slowly.
The pressure reduces slowly.
e) Remove the pipes and hoses.
f) Seal the connections for suction and pressure
nozzles using adhesive foil.
g) Insert the desiccant bag into the fi lter housing.
see also Section 3.2.1, Page 11
6.3 Re-commissioning
a) Check the condition of the machine (cleanliness,
cabling etc.).
b) Drain the preserving agents.
c) Remove the desiccant bag from the fi lter hous-
ing.
For installation see Section 5 Page 14
For commissioning see Section 6.1 Page 17