4 Installation

This chapter is provided for qualified personnel to install and interconnect the power components within the Argus
power system. Regarding battery installation, refer primarily to the manufacturer’s guidelines for more specific
information.

NOTE: To aid the user with installation, frequent reference is made to drawings located at the rear of this manual.

4.1 Safety

Precautions

Refer to the Important Safety Instructions near the front of this manual.

4.2 Tools

Required

Various insulated tools are essential for DC power system installation. Use this list as a guide:

• Battery lifting apparatus (as required)

• Electric drill with hammer action, 1/2" capacity

• Various crimping tools and dies, to match lugs used in installation

• Load bank of sufficient capacity to load largest rectifier into current limit

• Digital voltmeter equipped with test leads

• Cable cutters

• Torque wrench: 1/4” drive, 0-150 in./lb.

• Torque wrench: 3/8” drive, 0-100 ft./lb.

• Insulating canvases as required (2’ x 2’, 1’ x 1’, 3’ x 3’, etc.)

• Various insulated hand tools (see Figure 9) including:

-Combination wrenches

-Ratchet and socket set

-Various screwdrivers

-Electricians knife

• Battery safety spill kit (required for wet cells only) including:

-Protective clothing

-Face shields

-Gloves -Baking

soda

-Eye wash equipment

• Cutters and wire strippers 0.08 to 6mm

2

(#28 to #10 AWG).

Figure 9–Example of an insulated tool kit