Installation, 1 site prep and installation – Alpha Technologies Underground Battery Vault User Manual

Page 9

Advertising
background image

031-040-B0-002 Rev. B

9

Vault & Lid

Optional concrete pad
(4” to 6” thick)

Compacted backfi ll

Compacted
backfi ll

Drainage gravel

(6” deep typical)

For installations where the optional concrete pad is not used:

1. Excavate the site approximately 6” deeper than the overall height of the vault. The length and width

of the hole should be 4” to 6” more than the width and depth of the vault.

2. Use 6” of compacted gravel as a base for the vault. Level the gravel so the top of the vault is fl ush

with grade.

3. Finish installation by adding backfi ll and compacting.

For installations where the optional concrete pad is used:

1. Excavate the site approximately 6” deeper than the overall height of the vault. The length and width

of the hole should be 4” to 6” more than the width and depth of the vault.

2. Use 6” of compacted gravel as a base for the vault. Level the gravel so the top of the vault is fl ush

with grade.

3. Install shims on each side and end to prevent defl ection.
4. Add

backfi ll and compact to a depth of 8” below grade.

5. Build form around vault to make a 6” wide collar around the vault.
6. Once concrete sets, fi nish backfi ll to grade.

Undisturbed soil

2” PVC conduit for wiring
(provided by installer),
broken out of enclosure at
appropriate location for

installation.

2. INSTALLATION

2.1

Site Prep and Installation

Fig. 2-1 Typical site for UBV