INSTALLATION INSTRUCTIONS

TCHDRND1

For a downloadable Adobe Acrobat (.PDF) version of our Limited LIFETIME WARRANTY,
go to our website at www.ddtechglobal.com

MAINTENANCE & REQUIREMENTS:

• Always use two ROUND-POST HINGES on any one gate.

• Ensure the gate does not swing beyond 180˚.

• Each hinge must have equal tension at all times.

• Remove all other types of hinges and self-closing devices.

Do not lubricate these hinges with petroleum-based lubricants. Use only

powdered graphite.

• Never remove ROUND-POST HINGES from gate until spring tension is released.

• Do not physically alter hinge bodies by cutting, milling, machining or grinding any part.

• For safety, remove protruding bolts/screws after installation by cutting, grinding and/or filing.

fits

both

left

-

hand

or

right

-

hand

hinged

gates

•INSTR-TCHDRND1_1 11 11

TCHDRND1000PA

P

rocedure

In preparation for installation of the hinges, choose the appropriate round-post adaptors by

placing them onto the post to determine the correct fit. Each adaptor should fit neatly around

the diameter of the gate and the post. Discard unwanted adaptors.

1.

Insert the adaptors for the gate frame into the rear of the hinges, ensuring the location

‘lugs’ at the rear of the adaptors fit snugly into the hinges.

2.

Take the hinges and align/position them onto the gate to suit the style of latch used

(see Diagrams A & B).

3.

Take the hex-shaped screws (12g–24x25mm ) and secure the hinges to the gate. A pilot

hole of

3

/

16

"

(4.8mm) will be required. Note the need for hinge vertical alignment (level), as

shown in Diagram C. The wafer-head screws (10g–24x22mm) for the side-fixing legs are to be

installed once the gate is hung.

4.

Insert the post adaptors into the rear of the hinges.

5.

Take the gate and locate it into the desired position/height. You may need to prop up

and support the gate temporarily during installation.

6.

Ensuring the gate is correctly aligned with the fence (see Diagrams A & B), take the

remaining hex-head screws and secure the hinges (the gate) to the post. Again, pilot hole of

3

/

16

"

(4.8mm) will be required.

7.

Open the gate sufficiently to allow installation of the screws for

the side-fixing legs. Note there are four screws remaining for each
hinge. A pilot hole of

5

/

32

" (4mm) will be required

.

8.

Adjust tension: Remove the endcap at the “adjustable” end

of the hinge. Use the large slot-head screwdriver to depress and

turn the internal spring-loaded adjustor counter-clockwise. Hold the

desired tension and allow to rise back into retention sleeve. Replace

endcap.

The gate is now ready for use. Ensure the gate cannot swing beyond

180˚ through the line of the fence by installing a latch or ‘gate stop’.

Some important points concerning the installation of ‘ROUND-POST HINGES’:

• Note that each hinge has five different-sized adaptors to fit various diameters

of posts or gate frames.

• The adaptors in this pack fit the following diameters:

GATES

(to fit the small side of the hinge): 1

3

/

8

,

1

5

/

8

“ (35 & 41mm)

POSTS

(to fit the large side of the hinge): 1

7

/

8

“ and 2“

,

2

3

/

8

,

2

7

/

8

“ (48-51, 60 & 73mm)

• Wherever possible, keep the “adjustable end” of the hinge (indicated by screw in

endcap) facing up for ease of tension adjustment.

• The hinges should be installed as far apart vertically as is practical.

Tools required: Electric drill/cordless drill,

3

/

16

" (4.8mm) &

5

/

32

" (4mm) drill

bits, Phillips No. 2 screwdriver (hand & power),

5

/

16

" hex-head driver and

large slot-head screwdriver.

STRAIGHT

OFFSET

FLUSH-MOUNTED LATCHES

Maintain 180˚ alignment during installation

to ensure accurate, reliable closure.

CENTER-MOUNTED LATCHES

The hinge can be offset slightly to help align

the latch in the middle of the latch post.

D

iagram

a

D

iagram

B

Post

Gate

Post

Gate

LINE OF
FENCE

LEVEL

IMPORTANT

Keep top and bottom hinges

vertically aligned (level)

D

iagram

C

LINE OF
FENCE

Minimum gap between hinge post and gate:

3/4" (19mm).

Maximum gap: 1-3/8" (35mm).