BJM Pumps PGV220-575T User Manual

Page 26

Advertising
background image

START-UP REPORT FORM

Voltage supply at panel line connection, pump on

L1-L2

L2-L3

L3-L1

Amperage load connection, pump on

L1

L2

L3

FINAL CHECK

Is pump secured properly?

Yes

No

Was pump checked for leaks?

Yes

No

Do check valves operate properly?

Yes

No

Flow: Does station appear to operate at
proper rate?

Yes

No

Noise level:

Acceptable

Unacceptable

Comments:

Describe and equipment difficulties during start-up

Installed by:
Company:

Person:

Date:

Maintained by:
Company:

Person:


Date and time of start-up

Present at start-up:
( ) Engineer’s name

( )Contractor’s name

( ) Operator’s name

( ) others

Advertising