Mini-GASS User Manual

APPENDIX D

1. Flange Mounted with Integral Sampling Probe and Filter Blowback Installation

Flange mounted Mini-GASS

®

is designed to be stack mounted on 2", 3" or 4" pipe flange. The

integral sample probe and filter eliminates need for a heated umbilical line to connect stack
gas sampling probe to sample conditioning system.

The Mini-GASS system is attached directly to sample port flange by following the steps below:

1. Attach flange to sampling port using appropriate sized gasket and bolts.
2. Align flange holes with turnbuckle anchor at bottom. Install four appropriate sized
bolts and hand tighten all four bolts evenly. Tighten with wrench (see Figure 14).
3. Install sampling probe pipe into pipe flange by inserting non-threaded end of probe
pipe through flange (see Figure 15). Probe should extend into the center of the stack
and pointing slightly downward to allow any entrained liquid to drain back into the
stack.
4. Tighten probe pipe into flange with wrench.

pipe

5. Attach one end of turnbuckle to anchor at bottom of flange and fix pin in place with
cotter pin.

Flange

Turnbuckle

Figure 14

Figure 15

Probe Pipe