Installation, Install control panel and wiring – Poweramp AP SERIES AIR POWERED 4.2009 User Manual

Page 18

Advertising
background image

16

4111-0009 — Oct 2007

Jan. 2009

INSTALLATION

1. Mount the push button control panel (B) so bottom

of control panel-to-dock floor distance (C) is 48 in.
(1219.2 mm).

2. Install electrical disconnect panel (A) if not already

installed.

3. Install and connect the control wiring.

4. Re-install the air bag, air bag support pallet and

blower motor.

5. Connect the dock leveler power cable to the outlet

in the pit junction box. Refer to the electrical
drawings supplied with the dock leveler.

6. After all electrical connections in the pit have been

made, raise the leveler, disengage the
maintenance prop and allow the platform to lower.

Install Control Panel and Wiring

A— Disconnect Panel
B— Control Panel

(provided by others)
C— Distance, 48 in. (14 630 mm)

The electrical power must be OFF prior to electrical
installation. For maximum protection, use an OSHA
approved locking device to lock out all power
sources. Only the person installing the equipment
should have the key to unlock the power source.

Failure to follow these instructions may result in
serious personal injury or death.

DO NOT make any final electrical connections until
all welding has been completed. Failure to do this
may result in serious personal injury or death.

All electrical work — including the installation of the
disconnect panel, control panel, and final
connections to the pit junction box — must be
performed by a certified electrician and conform to
all local and applicable national codes.

B

A

C