Proper installation is the first step to operation. We recommend that your warmer be installed by an authorized Victory
Certified Installer.

Receiving

Prior to shipping, all Victory products are factory tested for performance and thoroughly inspected to ensure they are
free of any defects. Upon receipt, carefully examine the unit for any damage that may have occurred during shipping
and delivery. Any damage, discrepancies, shortages or overages should be noted on the carrier's Bill of Lading and
a freight claim must be filed immediately with the carrier. If damage is noticed after receipt, contact the carrier's local
terminal and file a freight claim. In either case, it is important that all original cartons, crates and interior packaging
material are saved until inspection has been made with the delivering carrier
.

Uncrating

Tools Needed : 3/4” Box Wrench, Adjustable Wrench, Level, Flathead Screwdriver, Box Cutting (or Carpenter) Knife

1. Take off the cardboard top capping by removing all clear tape and staples with a flathead screwdriver. Also remove
all staples at the bottom of the cardboard carton and skid.

2. Starting from the top of the cardboard carton, carefully take a box cutting knife and try to make one continuous cut
until you come to the wooden skid. Remove the cardboard carton from around the cabinet and discard.

*Note: An additional clear, plastic, protective wrap is applied directly to the exterior of all cabinets with glass doors.

3. Move cabinet as close to final location as possible before removing skid.

4. Remove the shipping skid by tipping the cabinet forward. Remove the shipping bolts with 3/4” box wrench while
the cabinet is held in one direction. Repeat this procedure while the cabinet is held in the opposite direction.

WARNING: The cabinet must be blocked and secured when removing the shipping skid.

5. Remove protective vinyl coating from all interior and exterior surfaces.

Warmer Location

Consider the following when selecting a location for your warmer:

1. Clearance - There must be a minimum clearance of 10” between the top of the warmer and the ceiling.

2. Floor Load - The floor on which the cabinet will rest must be even/level, free of vibration and strong enough to
support the combined weights of the cabinet plus the maximum product load.

3. Ventilation - Vent assemblies are supplied with each cabinet to assist in the warming process of foods. The
vent knob is located inside the warmer cabinet at the top. By turning the knob left or right, moisture within the
cabinet can be controlled.

Reach-In/Pass-Thru Cabinet Legs or Casters Installation

Warmers are shipped with 1/2” single stud mounted legs or casters.

WARNING: Cabinet must be blocked and secured when installing legs or casters.

1. Legs/Casters must be screwed in by hand into the threaded holes located on the case bottom. No threads of the
leg or caster stem should be visible.

*NOTE: Once the caster cannot be turned, using a 3/4” box wrench, tighten the nut in between the mounting plate and wheel of
the caster until it is snug.


2. Tilt the cabinet in one direction approximately eight inches and block it securely with several pieces of 2" x 4"
lumber or other suitable material.

3. Screw in the two left or right legs/casters.

4. Repeat this procedure to install the other legs/casters.

RECEIVING & INSTALLATION INSTRUCTIONS

RECEIVING & INSTALLATION INSTRUCTIONS

RECEIVING, UNCRATING & LOCATION INSTRUCTIONS

RECEIVING, UNCRATING & LOCATION INSTRUCTIONS

REACH-IN / PASS -THRU INSTALLATION INSTRUCTIONS

REACH-IN / PASS -THRU INSTALLATION INSTRUCTIONS

Advertising