Single modules are supported by two sections, or four load cells. A final grout plate elevation
adjustment should be made to match the mV/V outputs of the load cells to assure correct dis-
tribution of the scale's deadload among the four (4) points of support. Adjust the grout plate
leveling screws (equally) to match loadcells 1, 2, 3, and 4. When this has been completed,
ensure each loadcell grout plate is level to within .015" per foot.
NOTE: The loadcell numbering sequence shown is designed for interfacing Fairbanks INTA-
LOGIX technology instrumentation.
17: Perform a final check to all:
Loadcell grout plates are level to within .015" per foot.
All Load cells are vertical and plumb
Top flanges of the main beams are absolutely level and on the same plane as the end sec-
tions.
There is correct distribution of the scale's deadload among the loadcells.
All assembly hardware is secure and tight.
When complete, recheck to ensure all Grout Plates and Loadcells are plumb, square, and
level.