Installation

(for qualified installers only)

Travis Industries

4 1 2 2 1 0 4

9 3 5 0 8 1 1 7

Vent Requirements

!

Always maintain the required 1” clearance (air space) to combustible materials to prevent a fire hazard.
Do not fill air spaces with insulation.

!

The gas appliance and vent system must be vented directly to the outside of the building, and never
be attached to a chimney serving a separate solid fuel or gas-burning appliance. Each direct vent gas
appliance must use it’s own separate vent system.

This appliance is equipped only for
altitudes 0-2000 feet. However, our
in-house testing has shown that the
unit operated at altitudes to 8000 ft.

!

Failure to adjust the air shutter
properly may lead to improper
combustion which can create a safety
hazard. Consult your dealer or
installer if you suspect an improperly
adjusted air shutter.

When the vent passes through a wall,
a wall thimble is required. When the
vent passes through a ceiling, a
support box or firestop is required.
When the vent passes through the
roof, a roof flashing and storm collar
are required. Follow the instructions
provided with the vent for installing
these items.

Use a firestop spacer whenever
passing through a ceiling
(Duravent Part #963)

Vertical Termination
(Duravent Part # 991)

Use a roof flashing and storm collar
whenever passing through the roof
(Duravent Part #953 & #943 or #943S)

8-5/8"

Use a support box
on exposed vent

Vertical Vent

Requirements

Use a wall thimble
whenever passing
through a wall
(Duravent Part #942)

Horizontal Termination
(Duravent Part #984)

Maintain a minimum 1" clearance
from vent to any combustible
(vent is 6 5/8" diameter)

Minimum
Framing for
wall thimble

Horizontal Vent

Requirements

Minimum framing
for fire stop

8-5/8"

Maintain a minimum 1"
clearance from vent to
any combustible (vent
is 6 5/8" diameter)

Use one of the following 6-5/8" diameter co-axial gas direct vent systems:

Manuafacturer

S e r i e s

Simpson Dura-Vent

Model GS

Selkirk Hearth Products

Direct-Temp

American Metal Products

Ameri-Vent

N O T E

: Always use the high-wind cap for the type of vent you are using (if applicable)

Slide the vent sections together and turn 1/4 turn until the sections lock in place.

Screws are not required to secure the vent. However, three screws may be used to
secure vent sections together if desired.

High temperature sealant is recommended at the appliance starter section connection
(use high-temperature silicone or Mill-Pac®).

If disassembly is required, at time of re-assembly check to see if the vent creates a tight
fit. If it does not, apply high temperature sealant to the joints of the affected sections.

Horizontal sections require a 1/4" rise every 12" of travel

Horizontal sections require non-combustible support every three feet (e.g.: plumbing
tape)