2.6 Pre-installation requirements

Make sure that you have all necessary tools available:

• Allen key (4 mm)
• Small screwdriver
• Wrench for cable glands
• Wrench for wall mounting bracket (remote version only)
• Torque wrench for installing flowmeter in pipeline

2.7 General requirements

2.7.1 Vibration

2.7.2 Magnetic field

INFORMATION!
The following precautions must be taken to ensure reliable installation.

•

Make sure that there is adequate space to the sides.

•

Protect the signal converter from direct sunlight and install a sun shade if necessary.

•

Signal converters installed in control cabinets require adequate cooling, e.g. by fan or heat
exchanger.

•

Do not expose the signal converter to intense vibration. The flowmeters are tested for a
vibration level in accordance with IEC 68-2-64.

Figure 2-4: Avoid vibrations

Figure 2-5: Avoid magnetic fields