INSTALLATION INSTRUCTIONS, SINGLE SUPPORT

1 . Choose the proper location to install the AHL-GD Differential Pressure Flow Meter using AGA/ASME standards (or

equivalent) . Refer to the location diagrams

Figure 2

,

Figure 5

and

Figure 6

.

2 . Grind the surface of the pipe where the AHL-GD Differential Pressure Flow Meter is to be inserted to provide a clean area

for welding .

3 . Weld the supplied thread-o-let to the pipe using standard codes for your application (1/16 in . weld gap recommended) .

Take care to protect the threads during the welding process .

4 . Install the close nipple by threading it into the weld connector . Next, install the supplied 3-piece isolating ball valve .
5 . Mount the high pressure drilling machine onto the ball valve . Open the ball valve . Drill a hole through the pipe wall

according to

Table 2

.

Model/Sensor

Weld Connector

Drill Bit

AHL-GD (7⁄8 in .)

1-1/4 in .

1-1�8 in .

AHL-GD (1-1/4 in .)

1-1/2 in .

1-3�8 in .

Table 2: Single support drill bit size

OTEE:

N

There is no need for a drilling machine if it is not a hot tap installation or if the system is not pressurized .

6 . Having drilled through the pipe, withdraw the drill bit through the isolating ball valve . Once the drill bit has been

withdrawn, close the ball valve and dismantle the drilling machine . Ensure that there is no leakage at the valve and close

nipple connections . The ball valve is to remain completely closed until step 9 .

7 . Install the cage nipple assembly and packing gland with the threaded rods assembly by threading it into the isolating ball

valve . Align the arrow on the sensor head with the direction of flow . See

Figure 4

and

Figure 5

.

8 . Install the instrument valves (optional) at the pressure connections located on the AHL-GD Differential Pressure Flow Meter

sensor head . Ensure that the valves are fully closed before proceeding .

H

L

SCH/WALL

MOD/β
DIA/ID
CAP
DP
TAG

FLOW METERS
W/O

SCH/WALL

FLOW METERS
W/O

H

L

FLOW

FLOW

Field Weld

Figure 4: Flow indication arrow

9 . Open the isolating ball valve . Insert the AHL-GD Differential Pressure Flow Meter sensor into the pipe until it reaches the

opposite pipe wall . This should be done by turning the threaded insertion rods clockwise using a wrench .

10 . Connect the instrument lines to the sensor head valves . In turn, connect these lines to a gage or transmitter .