Setup 20

Installing a server blade

1.

Remove a 6U server blade blank.

2.

Install the server blade. When the server blade is fully inserted, it locks into place.

The default setting for server blades initiates automatic power up.

CAUTION: To prevent improper cooling and thermal damage, do not operate the server blade

enclosure unless all bays are populated with either a component or a blank.

NOTE: The first server blade must be installed into a server blade enclosure to facilitate naming the

server blade enclosure, the rack, and the interconnects. Complete the system configuration before

installing additional server blades.

Completing the configuration

To complete the server blade and HP BladeSystem configuration, refer to the hardware installation and

configuration poster that ships with the server blade enclosure.