6. READY-TO-RUN RTR-SERIES

PIPING INSTALLATION

DOMESTIC WATER PIPING

1. Connect the cold water supply to the pipe labeled COLD

WATER.

2. Connect the HOT WATER piping to the domestic hot water

system.

3. Make an 8-inch “heat trap” on the HOT WATER outlet as

shown in the diagram. This will reduce standby losses from
heat migrating up the piping.

4. When all domestic water piping is complete, open the cold

water supply and allow some water to enter the tank. Look
and listen for signs of leaks and repair as necessary before
continuing.

Note: If installing on a city supply, ensure a dedicated
Thermal Expansion tank (Therm-X-Trol

®

or equivalent) is

used.

5. Install a blowdown tube on the T&P relief valve outlet.

Plumb to within 6 inches above a floor drain or as directed
by plumbing code.

BOILER PIPING

1. Plumb the BOILER SUPPLY line. The circulator and flow

check are factory installed

2. Pipe the BOILER RETURN connection to the boiler return

line.

Be sure the return line is NOT

plumbed to the suction side of any

heating circulators. This may require moving the

heating circulator off the boiler tapping on packaged

boilers. Failure to do so will result in overheating and

tank damage when the heating system is in

operation.

3. After completing the boiler piping, slowly open the boiler fill

valve and pressurize the heat exchanger loop. Check for
leaks and repair as necessary. Proceed to the appropriate
wiring section in this manual.

If installing on city water supply a

properly sized THERM-X-TROL

®

is

required with the BoilerMate

®

and should be installed as set

forth in the THERM-X-TROL

®

product installation manual.

TOP VIEW

CIRCULATOR

BOILER SUPPLY

BOILER RETURN

SIDE VIEW

DRAIN VALVE

T&P RELIEF VALVE

OUTLET

HOT WATER OUTLET

COLD WATER INLET

LEFT SIDE . . . . . . . . . . . . 1”

RIGHT SIDE . . . . . . . . . . . 1”

TOP . . . . . . . . . . . . . . . . . 9”

REAR . . . . . . . . . . . . . . . . 1”

FLOOR . . . . . . . . . . . . . . . 0”

FRONT . . . . . . . . . . . . . . . 1”

Clearance From Combustible Surfaces

LEFT . . . . . . . . . . . . . . . . . 12”

RIGHT. . . . . . . . . . . . . . . . 12”

FRONT . . . . . . . . . . . . . . . 30”

HEAD ROOM . . . . . . . . . . 36”

REAR . . . . . . . . . . . . . . . . 1”

Recommended Clearance For Servicing

Advertising
This manual is related to the following products: