SHIPBOARD PUMP

REBUILD PROCEDURE

(Requires B1-10M 5/8 Hydraulic Kit)

1. Remove B1-28 Snap Ring at top of pump cylinder

2. Fluid level under Lift Ram (B1-26 10M SS) mush have approximately 1.5 – 2” under Lift

Ram U-cup. Procedure is as follows…Place shop rag around the top of the pump to prevent

oil splatter. Firmly strike the top of the Lift Ram with a rubber mallet. The fluid back pres-

sure will cause the B1-01 C Center Cylinder to lift out. Remove the lift ram ,part B1-26

10MSS.

3. Remove B1-04 R/L pump straps.

4. Lift out B1-17.5SS pump piston.

5. Remove both the B1-42 release guides and B1-13SS release plunger.

6. Remove the B1-20 hydraulic plugs (4 plugs), along with the B1-35, B1-33, B1-31 springs.

7. Remove B1-16 balls (3) and the B1-13 RP release plunger.

8. Keep all parts clean during the reassemble process.

9. Replace all O-rings, U-cups, Wipers, Springs, and Balls.

10.

Reassemble pump in reverse order of part removal, applying o

ne drop of non-detergent

SAE 30 oil to all o-rings, wipers and seals.

11. Fill pump in the upright position with Dextron Type 2 Automatic Transmission Fluid. Fill

to the bottom of the B1-20 filler plug, with the Lift Ram in the lowered position.

12. Open B1-11 Bleeder Valve 1/8 turn to remove air trapped under the pump piston. Close

valve when fluid runs free of air. Do not over tighten.

13.

Reinstall pump and adjust B1-38 Restrictor screw to set lowering speed.