WIKA A2G-45 User Manual

Page 12

Advertising
background image

WIKA operating instructions air2guide model A2G-45

GB

12

40389228.01 09/2012 GB/D/F/E/I

Zero point adjustment

Attention!

Connect the voltage supply one hour before making the

zero point adjustment.

Remove both hoses from the pressure connections ⊕ and ⊖.

Press both the "up" and "down" buttons simultaneously, or select

"Zero" in the setting menu:

⇒ the green LED switches off and "Zero" is shown in the display.

Wait until the green LED switches back on, then reconnect the ⊕ and

⊖ pressure connections.

In normal operation, we recommend that a zero point adjustment is

carried out every 12 months.

Span calibration

Attention!

Connect the voltage supply one hour before making the

span calibration.

A reference pressure measuring instrument is needed for the span

setting.

The span should not be set without pressure being present. If the span

is set with either no test pressure, or too-low a pressure, the instrument

will lose its accuracy and no longer give correct measured values.

If this should occur, select the menu point "Span" and then select

"Reset", in order to reset the span setting.

6. Commissioning, operation

Advertising