Unit Isolation —

Where extremely quiet operation is

essential, install isolators between floor and base of unit, or

between ceiling and top section of unit.
Be sure that unit is level and adequately supported. Use

channels at front and sides of unit for reference points when

leveling.

Refrigerant Piping Access —

The 524J Series units

come with standard knockouts for refrigerant piping. These

knockouts are located on both sides of the unit for installation

flexibility. The standard knockouts provide sufficient access to

the unit’s coils for all 524J*07A, 08A, 12A, 14A and 16A units

as well as the 524J*07H, 08H, 12H units. See Fig. 7 for the

positions. Recommended access hole use is also listed for all

units. Note that Fig. 7 shows the access holes on the control-

box side of the unit; this is the side of the unit with the coil

headers, so it is used most often for piping access.

Refrigerant Piping —

See Tables 1A – 1D for refriger-

ant pipe connection sizes. For ease in brazing, it is recommend-

ed that all internal solder joints be made before unit is placed in

final position.
The 524J direct-expansion units have internal

factory-installed thermostatic expansion valves (TXVs),

distributors, and nozzles for use with R-410A. See Table 2

for part numbers. Knockouts are provided in the unit corner

posts for 524J refrigerant piping. See Fig. 7, which also lists

recommended knockouts and access holes to use for each

524J unit size. Recommended fittings are listed in Table 3.
The sensor bulb capillary tubes must be routed from the TXVs

inside the unit through one of the piping access holes. Clamp

the TXV sensor bulb on a vertical portion of the suction line,

outside the unit. See Fig. 8.
NOTE: Be sure to remove the styrofoam shipping pad from

the TXV. Verify that it has been removed. See Fig. 4.

The 524J Series evaporator coils have a face-split design.

Ensure that lower circuit of coil is first on/last off when

connected to the condensing unit and/or system controls. See

Fig. 8.
External TXV equalizer connections are provided and

factory-brazed into the coil suction manifolds.
If suction line must be horizontal, clamp bulb to suction line at

least 45 degrees above bottom, at approximately the 4 o’clock

or 8 o’clock position. See Fig. 9.

Fig. 7 — Refrigerant Piping Access Holes

IMPORTANT: Do not bury refrigerant piping underground.

IMPORTANT: Never attach the sensor to the suction

manifold. Do NOT mount the sensor on a trapped portion

of the suction line.

4
3
2
1

UNIT

USE HOLE

NUMBERS

524J*07A, 08A

524J*07H, 08H

1, 3