4 Installing the Air Locker

21

c Check that no part of the seal housing tube comes in contact with

the moving differential components. 10mm [3/8”] should be
considered adequate clearance. Gently bend the tube away from
moving parts if necessary.

4.11

Bench Testing the Air Locker

c To test the Air Locker; when 620kPa [90 PSI] shop air is applied to

the seal housing tube, the Air Locker should engage.

c Check all fittings and the seal housing for air leaks.
c Rotate the differential carrier by turning the pinion flange whilst

applying air pressure.

NOTE : An accurate way to test for air leaks is to fit a shut-off

valve to an air pressure gauge (ARB part # ALTG01).
Once 620 KPA [90 PSI] is reached close the valve,
disconnect the air hose, and watch to see if there is any
drop in pressure. If so, this will indicate an air leak.
(Fig.13.)

Figure 13.









c If a leak is found to be present, spray a soap and water mixture

onto the bulkhead air fitting. Bubbles should appear at any leak
points.

NOTE : Do not spray this soapy mixture inside the differential.

c Check that leaky fittings have been adequately tightened.
c Disassemble, clean threads, and reapply thread sealant if leaking

persists.