5 installing the air system, Connection to the bulkhead fitting – ARB RD129 User Manual

Page 28

Advertising
background image

5 Installing the Air System

26

5.3

Connection to the Bulkhead Fitting

c Trim the air line to length using a sharp knife.
c Insert the support spring over the end of the air line - small end first.

(Fig.15.)

c Insert the outer compression nut over the air line.
c Insert the 5mm [0.197”] ferrule over the end of the air line. Leave

approx. 5mm of tubing between the ferrule and the end of the tube.

Figure 15.













c Insert the support tube all the way into the end of the air line.

HINT : If the support tube is too difficult to insert, place the

end of the air line into a cup of boiled water to soften
the tubing.

c Insert the tube end all the way into the center compression nut.
c Screw on the outer compression nut and tighten. The ferrule and

support tube are now permanently attached.

c Assemble the support spring over the outside of the outer

compression nut.

c Secure any loose sections of tube with a cable tie.

Advertising