MOLD ORDERING
Complete information is necessary to insure delivery of the mold.
Accurate engineering drawings or sketches are necessary to insure the accuracy of the mold
being built. Molds will not be manufactured until ALL dimensions are clarified.
IMPORTANT
All information on the order form must be complete before manufacturing of mold will begin.
Use hopper size chart. The size of the opening in which the mold bolts up to is critical. There
are several different size hopper openings currently in the field. WE NEED THE DIMENSIONS
OF THE OPENING TO PROPERLY FIT THE MOLD TO YOUR HOPPER. Please write these
dimensions down in the space provided. This will allow us to ship your mold as soon as posĆ
sible.
TERMINOLOGY CURB AND GUTTER
BACK OF CURB
The distance from the grade to the top of curb on the back fill side.
TOP OF CURB
The distance from the back of curb to the face of curb.
FACE OF CURB
The slope on the curb face, which must be toward the gutter.
FLOW LINE
The distance from the grade to the low point in the gutter.
GUTTER
The sloped area or PITCH. This can be measured in inches/foot or the
intersection of the FACE OF CURB and the GUTTER surface.
TOE OF CURB
The distance from the grade to the top of the gutter.
BATTER
Batter is added to the base to insure the curb will stand. If there is no
batter, MBW Inc. cannot guarantee the curb will stand.
Typical minimum batter dimensions.
BACK OF CURB
12" = BATTER
1/2"
BACK OF CURB
18" = BATTER
3/4"
TOE OF CURB
6"
= BATTER
1/4"
BASE
The distance across the bottom of the curb minus the batter.
RADII
Corners of mold can not be made without a bend radii. Minimum raĆ
dius is 1/4".
BASE
BACK OF
CURB
TOP OF
CURB
FACE OF CURB
FLOWLINE
GUTTER
TOE OF
CURB
BATTER GUTTER
BATTER CURB
RAD. 1
RAD. 2
RAD. 3