9. Retaining Ring (1I) installed into the groove provided

in the output Shaft (1A). This retaining Ring (1I)
should never be reused in a repair or rebuild.

EYE PROTECTION SHOULD BE WORN DURING THIS PROCEDURE.

10. A soft metal punch should be used to insure that this

retaining ring (11) is completely seated in the groove
of the Output Shaft (1A).

EYE PROTECTION SHOULD BE WORN DURING THIS PROCEDURE.

11. Upon completion of step 10, rap the internal end of

the Output Shaft (1A) twice with a piece of soft metal

rod. This will release the preload which was on the
bearings.

Carrier Sub-Assembly Procedure

1. Apply a coat of grease or petroleum jelly to Cluster

Gear bore.

2. lace sixteen Needle Rollers into Cluster Gear bore.

3. Place Spacer Washer into opposite side of Cluster

Gear and against Needle Rollers.