SECTION 4 - MACHINE OPERATION

3121212

– JLG Lift –

4-7

3. To lower platform, depress FUNCTION ENABLE BUTTON

(green) and PLATFORM DOWN button (bottom, white but-
ton)
on control panel simultaneously. Upon reaching
desired elevation level release PLATFORM DOWN and
FUNCTION ENABLE buttons.

4.5 QUICK-CHANGE PLATFORM

The AMI model is equipped with quick-change platform mounts
which will allow quick removal and installation of the currently
available quick-change platforms. The following procedures
describe platform removal and installation:

Platform Removal

1. Remove both lower mount pins securing the lower plat-

form support rail to the platform lower mount.

2. Remove both upper mount pins securing the upper plat-

form support rail to the platform upper mount.

3. Using either suitable lifting equipment capable of lifting the

weight of the mounted platform, or another person, swing
the lower platform support rail forward, away from the
mast to clear the platform lower mount, then lift the upper
platform support rail up and out of the platform upper
mount. Move the platform clear of the machine and care-
fully set the platform on its base out of the way.

Platform Installation

1. Using either two people or suitable lifting equipment capa-

ble of lifting the weight of the unmounted platform, lift the
platform and set the platforms’ upper support rail into the
upper platform mount on the mast.