SECTION 4 - MACHINE OPERATION

3121165

– JLG Lift –

4-11

4.10 TIE DOWN/LIFT LUGS

When transporting the machine, the platform extension must
be fully retracted and the platform fully lowered in the stowed
mode with the machine securely tied down to the truck or
trailer deck. There are two tie-down/lift lugs located at the rear
of the machine for lifting and tieing down. There is a single tie-
down lug at the front of the machine. This lug is designed for
tieing down only. Do not attempt to lift machine from the front
lug.

LIFTING THE MACHINE FROM THE SIDES USING A FORK TRUCK IS NOT REC-
OMMENDED BY JLG. IN THE EVENT THAT THE MACHINE NEEDS TO BE LIFTED
FROM THE SIDES CAUTION MUST BE USED TO AVOID JAMMING THE POT HOLE
PROTECTION BARS UP AGAINST THE FRAME.
EVERY TIME THE MACHINE IS LIFTED FORM THE SIDE, BE SURE AND TEST THE
POT HOLE PROTECTION SYSTEM BEFORE THE MACHINE IS PUT BACK INTO
OPERATION.

4.11 LIFTING

In the event that the machine must be lifted, there is a forktruck
pocket located at the rear of the machine. The machine can also
be lifted using a proper spreader bar and straps/chains. Refer-
ence Figure 4-3., Lifting and Tie Down Diagram.