12. Tighten the cap screws evenly and progressively in

rotation to the specified torque value. (See Table 5-1,
Cylinder Head and Tapered Bushing Torque Specifi-
cations.
)

13. After the screws have been torqued, tap the tapered

bushing with a hammer (16 to 24 oz.) and brass
shaft (approximately 3/4” in diameter) as follows;

a. Place the shaft against the cylinder rod and in

contact with the bushing in the spaces between
the cap screws.

b. Tap each space once; this means the tapered

bushing is tapped 3 times as there are 3 spaces
between the cap screws.

14. Retorque the cap screws evenly and progressively

in rotation to the specified torque value. (See Table
5-1, Cylinder Head and Tapered Bushing Torque
Specifications.)

15. Remove the cylinder rod from the holding fixture.

16. Place new guide locks and seals in the applicable

outside diameter grooves of the cylinder piston.
(See Figure 5-19., Piston Seal Kit Installation)

17. Position the cylinder barrel in a suitable holding fix-

ture.

EXTREME CARE SHOULD BE TAKEN WHEN INSTALLING THE CYL-
INDER ROD, HEAD, AND PISTON. AVOID PULLING THE ROD OFF-
CENTER, WHICH COULD CAUSE DAMAGE TO THE PISTON AND
CYLINDER BARREL SURFACES.

18. With barrel clamped securely, and while adequately

supporting the rod, insert the piston end into the
barrel cylinder. Ensure that the piston loading o-ring
and seal ring are not damaged or dislodged.

19. Continue pushing the rod into the barrel until the cyl-

inder head gland can be inserted into the barrel cyl-
inder.

20. Secure the cylinder head gland using the washer

ring and socket head bolts.

21. After the cylinder has been reassembled, the rod

should be pushed all the way in (fully retracted) prior
to the reinstallation of any holding valve or valves.

Figure 5-20. Tapered Bushing Installation

Figure 5-21. Seating the Tapered Bearing

Figure 5-22. Poly-Pak Piston Seal Installation

Figure 5-23. Rod Assembly Installation

Advertising
This manual is related to the following products: