1. Remove all load from the platform. Never block the lift when loaded, only when

empty.

2. Raise the lift platform fully by depressing the “UP” button.

3. The maintenance leg is stored on the clevis end of the lift. Place the end of the

maintenance leg in the socket on the base frame of the lift.

4. Begin lowering the platform by activating the “DOWN” valve until the scissors

mechanism is resting on the maintenance leg. Continue activating the “DOWN” valve
five to ten seconds to relieve the pressure in the line.

5. Check to be certain that the maintenance leg is securely in the socket on the platform

and the socket on the base frame.

DANGER

!

HIGH VOLTAGE!! Disconnect and/or lock out the electrical supply to the
power unit prior to any installation or maintenance being performed.

6. To remove the maintenance leg, raise the platform by activating the “UP” valve to

provide sufficient clearance for the removal and storage of the maintenance leg.