RESIDENTIAL PANEL INSTALLATION

INSTALLING FIRST PANEL

INSTALLING INSIDE CLOSURES

INSTALLING

PANEL CLIP

STEP

1

STEP

2

FASTENER

INSIDE CLOSURE

w/ TAPE SEALANT

TAPE SEALANT

INSIDE CLOSURE

ROOF PANEL

1. Apply a row of Tape Sealant across the top leg of the Eave Molding along the width of

the building.

2. Align and place Inside Closures over the Tape Sealant. It is critical that Inside Closures

are square to building as this will control the alignment of the panels. (See page 24 to

check building square).

3. Apply a row of Tape Sealant across the top of the Inside Closure (Not shown for clarity).

1. Install the first panel over the Inside Closure to allow for desired overhang. Make sure the panel

is square to the eave and rake.

2. Fasten through panel, closure, and sealants into decking with appropriate amount of fasteners to

meet local building code. (See fastening patterns on pages 13 and 14). Fasteners must penetrate

closure and sealant.

3. After securing panel at eave, repeat the fastening pattern at the appropriate spacing to meet local

building codes.

NOTE:

-Eave Molding, Gutter and Valley Flashings must first be installed before panel installation can begin.

-Panels can be installed going from either letf to right or right to left / looking from eave to peak.