Damper System Operation

30

Initial Setup

Operation

Initial Setup

The initial setup tasks include the following:

•

Determine what types of fixtures/grips will be needed to secure the
specimen into the load frame.

•

Determine the position of the load frame crosshead.

•

Prepare the fixtures/grips, specimen, and data acquisition transducers.

•

Ensure that the load cell is properly rated for the test and that it is aligned
with the actuator.

•

Ensure the appropriate servovalve configuration is set up properly.

•

Ensure that the servovalve and feedback control cables are properly
connected.

Detailed information on these tasks can be found in the load frame product
manual.