4 • 65-2461RK PPM Hexane Transmitter

Test Points

The test points are in the lower left corner of the amplifier on either side of the gas select
jumper strip (see Figure 1). The test points produce a 100 to 500 mV output that
corresponds to the transmitter’s 4 to 20 mA output. Use the test points and a voltmeter to
measure the amplifier’s output during the start-up and calibration procedures. The black
test point on the left is the negative (-) test point and the red test point on the right is the
positive (+) test point.

Junction Box

Use the junction box to install the transmitter at a mounting site that is remote from the
controller. The junction box also protects the amplifier and wiring connections made to
the amplifier. Use the top 3/4 inch conduit hub to connect wiring from the amplifier to the
controller. Use the cover on the front of the junction box to access the interior of the
junction box. The detector and amplifier are factory installed in the junction box.

Installation

This section describes procedures to mount the ppm hexane transmitter in the monitoring
environment and wire the transmitter to a controller.

Mounting the PPM Hexane Transmitter

Figure 2: Mounting the PPM Hexane Transmitter

J Box

Rubber
Spacers,
3X

.75

2.70

.38

3.65

3/4 NPT Female

Hexane

Detector

3/4 x 1/2 Reducing

Bushing

7.5 max