21. COMMISSIONING REPORT

INSTALLING CONTRACTOR: …………………………………………………………….

COMMISSIONING TECHNICIAN: ………………………………………………………..

ADDRESS: …………………………………………………………….

CITY: …………………………………………………………….

STATE/PROV: …………………………………………………………….

PHONE: …………………………………………………………….

CELL: …………………………………………………………….

DATE INSTALLED: ……………………………

PROJECT NAME: …………………………………………………………….

PROJECT CITY: …………………………………………………………….

HEATER MODEL #: …………………………………………………………….

HEATER SERIAL #: …………………………………………………………….

THIS APPLIANCE HAS BEEN FACTORY TESTED PRIOR TO SHIPMENT.
HOWEVER, IT IS NOT A “PLUG-IN” APPLIANCE AND REQUIRES FIELD ADJUSTMENT
AND COMMISSIONING TO ENSURE SAFE AND EFFICIENT OPERATION.

A QUALIFIED GAS SERVICE TECHNICIAN MUST COMMISSION THE APPLIANCE AND
COMPLETE THE COMMISSIONING REPORT.

CONFIRM THAT THE APPLIANCE IS INSTALLED ACCORDING TO ALL LOCAL AND NA-
TIONAL CODES AND THE INSTRUCTIONS IN THIS MANUAL.

ENSURE THAT SITE CONDITIONS MEET THE SPECIFICATIONS IN THIS MANUAL RE-
GARDING:

 SUSPENSION
 CLEARANCES TO COMBUSTIBLE MATERIAL
 VENTING AND AIR SUPPLY
 ELECTRICAL SUPPLY, WIRING, AND CONNECTION
 GAS CONNECTION, SUPPLY AND MANIFOLD PRESSURE


THIS COMMISSIONING REPORT MUST BE SUBMITTED TO OUR TECHNICAL SER-
VICES DEPARTMENT PRIOR TO ANY CALL FOR TECHNICAL ASSISTANCE.

FAX THE COMPLETED REPORT TO 1-866-361-0523