Testing – Rockwell Automation 2100 CENTERLINE Smoke Detector Unit User Manual

Page 4

Advertising
background image

Publication 2100-IN046B-EN-P—November 2001

4 CENTERLINE Motor Control Centers Bulletin 2100 Smoke Detector Unit

Testing

To test the smoke detector unit and circuits:

1. Unlatch and open the smoke detector unit door.

2. Turn the selector switch clockwise to the “ON” position.

3. Refer to the smoke detector manufacturer’s installation

instructions, supplied with the unit documentation, for testing
the “sensitivity level.” Hold a magnet on the “TEST HERE”
position on the smoke detector head as described by the
manufacturer until the “SMOKE ALARM” pilot light illuminates
(approximately 7 to 15 seconds). If the “SMOKE ALARM” pilot
light does not illuminate after 30 seconds, a problem may exist,
such as a loss of AC or DC voltage, a blown fuse, an improper
connection between the smoke detector and the socket, or a
defective smoke detector. Repeat the test procedure if the
“SMOKE ALARM” pilot light does not illuminate.

4. When finished, turn the selector switch counterclockwise to the

“OFF-RESET-” position. Close and latch the unit door. Wait 20
seconds in the “OFF-RESET-” position before turning the unit
on.