Install magnets, Shaft install, Wn in refer to figure 3. do – Great Plains Shaft Monitor 2N-30 User Manual

Page 3

Advertising
background image

Install Magnets

Front Page

Part Lists

Great Plains Manufacturing, Inc.

3

2014-08-27

Front Page

Part Lists

197-114M

Install Magnets

Shaft Install

Refer to Figure 3

1.

De-grease and dry the seed box shaft

.

2.

Rotate the shaft so that two faces are vertical, and
two are horizontal.

3.

Select one new:

197-270D SHAFT MONTITOR HOSE

4.

Slip the shaft monitor hose

over the shaft

and

center approximately with the middle of the sensor
mount

. If necessary, trim hose to fit between the

shaft lock collars.

5.

Select two new:

10630171101 SHAFT MONITOR MAGNETS

6.

Slip each magnet

over the hose

, and position

as shown in figure 3. Run each magnet clamp up
against each lock collar, then tighten the clamps.

7.

Slide the reed sensor switch

in the mount side-to-

side, and front-to-back until it is centered between
the magnets and tighten the #4-40 screws

.

8.

Repeat steps 1 through 7 to install the other sensor
and magnets.

Refer to Figure 4

• Typical installation.

Figure 3

Magnet on Shaft

34212

2

16

14

18

17

12

14

13

15

U

D

F

B

L

R

3

2

13

13

2

12

14

14

13

15

16

Figure 4

Magnet/Sensor Clearance

36404

Advertising
This manual is related to the following products: