Amico Pipeline

Control Board Replacement

If necessary, the control board replacement can be performed while the manifold is in service. However, this should only

be done by qualifi ed technicians experienced in servicing medical equipment.

1. Remove two top screws at the base of the display board bracket and bend the display board assembly back.

2. Disconnect power supply.

3. Remove the screws located on the circuit board, which detaches it from the front plate. Note orientation of the

old circuit board and remove the wiring, one at a time and connect each wire to the appropriate terminal on

the new board.

4. Install the circuit board and fasten the screws to secure it, turn bracket up and then fasten the two screw at the

base.

5. Reconnect power supply to the manifold cabinet.

6. Check the correct operation of the circuit board by simulating a bank switch over a couple of times.