5XPT SLIDING GLASS DOOR INSTALLATION INSTRUCTIONS


Section III: Perimeter Accessory Fabrication for Assembled Doors

A. Subhead Installation




1. Subheads to be field cut to length (cut length = [overall frame dim. + 1/8”], unless shown

otherwise) and installed.

2. Make reference to Section I. D., for perimeter anchorage considerations.

3. Shim as required to allow for the proper engagement of the sliding glass door head into the

subhead. (See Fig. C)

The subhead is now ready to install the Sliding Glass Door frame.
(See the assembly instructions (SECTION VI) for assembly of the Sliding Glass Door frame)

When preparing subframe for anchorage into the building opening, please
make note of plumb line alignment of subhead to sill starter possibilities as
shown in examples below.

Plumb Line

Shim

Fig. C