Prepare the burner for start-up – Beckett CG50 User Manual

Page 17

Advertising
background image

17

CG15, CG25, CG50 Burner Manual

Prepare the Burner for

Start-up

Start-up Checklist

Verify the following before attempting to start
the burner.

1. General

Carefully read and become familiar with the manual,
fl ame safeguard control instructions, sequence of
operation, pertinent wiring diagrams, gas system
layout, insurance requirements, other controls and
valve literature pertinent to the installation.

Follow the appliance manufacturer’s start-up
procedures (when available).

Inspect the combustion air supply and exhaust venting
and verify that they are free of obstructions and
installed and sized in accordance with all applicable
codes.

Notify appropriate personnel to schedule start-up (gas
utility, owner, operators, subcontractors, etc.).

2. Gas Supply Piping

Insure that the gas piping is properly sized and has
been inspected by the gas utility, leak tested at all
joints, and purged.

To protect the gas train and controls, insure that a drip
leg or dirt pocket has been properly installed.

Insure that the fuel gas being supplied is compatible
with the burner specifi cation and is available at the
correct regulated pressure. (See burner name plate
and specifi cation sheets).

Insure that the vent lines for the diaphragm valves have
been run to the outside and properly terminated.

Use RWB recommended maximum pipe lengths for
good light-off (Figure 8A/B).

3. Electrical

Insure that all wiring has been completed and complies
with the National Electric Code NFPA 70 and local
requirements.

Refer to Figure 1 and verify that the electrical supply
to the burner matches the voltage specifi cation on the
label.

4. Boiler or Appliance

Insure that the fl ue passages and combustion area
have been thoroughly cleaned and are in good
condition.

Set the breech damper to the required position for
system operation.

Fill the appliance with water (boilers).

Check all safety and operating controls for correct
application, installation, wiring, and operation.

Insure that the maximum capacity of the appliance is
compatible with the specifi ed burner input fi ring rate.

5. Burner - See Replacement Parts Illustration for
Familiarization

Insure that the gas burner model and capacity meet
the requirements for the installation.

Insure that the gas train meets operating specifi cations,
all safety codes and insurance requirements.

Refer to Table 3 and Figures 10A and 10B to insure
that the burner air damper is positioned for initial start-
up preliminary settings.

Insure that the burner is securely mounted in the
appliance with the pressure fi ring plate and all gaskets
in place for pressurized chamber applications.

Section: Prepare the Burner for Start-up

Professional Installation
and Service Required

Incorrect installation and mishandling of start-

up could lead to equipment malfunction and

result in asphyxiation, explosion or fi re.

This burner must be installed and prepared for start-
up by a qualifi ed service technician who is trained
and experienced in commercial gas burner system
installation and operation.
Carefully follow the wiring diagrams, control instruction
sheets, fl ame safeguard sequence of operation,
test procedures and all appliance manufacturer’s
directions that pertain to this installation.
If any of these items are not clear or are unavailable,
call Beckett at 1-800-645-2876 for assistance.

y

y

y

Delayed Ignition, Explosion
and Fire Hazards

This is a direct spark ignition burner and

by code requirements must have a primary

control with a 4-second fl ame establishment

period. Exceeding 4 seconds could result in

delayed ignition, explosions and fi re.

Always verify the primary control has a 4-second fl ame

establishment period by carefully following the control

manufacturers’ confi guration instructions.
Example: Honeywell RM Series requires clipping and

removing the JR1 resistor.