WARNING: When threading the process material through the rollers, follow
the material path symbol on the front of the sensor. If a force is applied to the
middle sensor roller in the incorrect direction, damage could result.

4. Install the sensor in the desired position at the measuring location using the

provided mounting holes.

5. Allow approximately ten minutes for thermal stabilization of the sensor.

6. Thread the process material through the measuring and guide rollers, following

the material path symbol on the front of the sensor.

WARNING: When threading the process material through the rollers, follow
the material path symbol on the front of the sensor. If a force is applied to
the middle sensor roller in the incorrect direction, damage could result.

NOTE: Since ZERO and GAIN adjustments are always performed

statically, the readings may differ under dynamic load.

7 Hang a weight that corresponds to e.g. 10% of the tension range from the

process material.

8. Connect a volt meter to pins 4 and 5 of the connector on the rear side of the

unit.

9. Adjust the potentiometer, which you can reach through the ZERO hole in the

housing, with a screwdriver (with a point width of max. 1.9 mm) until the

display of the connected volt meter reads,

for example:

Sensor model TS2 - 200:

Weight 20 g = Display 0.100 V for the TS2 standard version

or

Weight 20 g = Display 1.00 V for the TS2 version with 10 V output signal.

WARNING: Do not insert the screwdriver at an angle as this may damage
the potentiometer.

!

!

!