3 Installation

3.1 Mounting rack assembly

Both the mounting racks along with the cutting mills are installed one above
the other with the p-19 below and the p-25 on top. The rack for the p-25 is
mounted in alignment with the rear side. Both the racks are joined using the
supplied M10x110 screws, the 10.5 washers and nuts. Washers are placed
to doubly secure the screw head and nut.

3.2 Feed funnel assembly for p-25

The funnel is mounted on the p-25 using four M5 screws and supporting
washers.

3.3 Extension tube assembly for p-19

With the thick side pointing downwards, the extension tube is mounted on
the inlet tube and tightened with the knurled screw at the bottom.

3.4 Sample splitter assembly for p-25

Both the levers on the clamping ledge below the p-25 are positioned
forward and the sample splitter along with the projecting metal edges is
slid into the grooves of the ledge. Finally, the levers are toggled back-
wards and the sample splitter is clamped tightly.
The control box for the sample splitter is located on the side of p-25.
Connect the 2-pole plug to the socket at the bottom of the sample splitter
and lock it.