2. INSTALLATION

Page 16 of 82

AERCO International, Inc. • 100 Oritani Dr. • Blauvelt, New York 10913 • Phone: 800-526-0288

VD2: 02/28/14

OMM-0003_0D

AC-105

7) If the Valve is controlling steam, ensure that the steam line is properly trapped to prevent

accumulation of condensate ahead of the Valve.

8) Install Shutoff Valves (metal-seated, gate-type) upstream and downstream of the Control

Valve to permit removal from the line for maintenance.

9) Pressure gauges should be installed on both sides of the Control Valve as shown in Figure

2-1 (steam) or Figure 2-2 (hot water).

10) The gauge on the high pressure side of the Valve is for adjustment and maintenance

purposes. The gauge on the low pressure side is to ensure that the correct pressure is
being introduced to the Control Valve. For either steam or water flow, the low side gauge
denotes the pressure of the fluid in the line which may create a hazardous condition.

11) A temperature gauge should be installed in the high pressure side of a hot (boiler) water

line as shown in Figure 2-2.

12) Install the Control Valve with the arrow on the Valve Body pointing in the direction of flow.

13) After the Control Valve has been installed in the steam or hot water line, ensure that all

piping connections are secure and leak tight.

14) This completes the installation procedures for the Control Valve. Proceed to the next

paragraph titled ELECTRONIC CONTROL SYSTEM INSTALLATION.

Figure 2-1. Recommended Control Valve, CXT-E Installation For Steam Flow

STRAINER WITH 0.020

MEST STAINLESS

STEEL BASKET,

SHOWN ROTATED

DOWN 90 DEGREES

FOR CLARITY

PIPING PITCH DIRECTION

1 TO 40 RATIO MINIMUM