FloAire HOT WATER COIL MODULE User Manual

Page 11

Advertising
background image

FLUID IOM

Shut-off Valve
w/Hose Connection

Throttling
Valve

Vent
Hole

Inhibited
Glycol
Reservoir

Pump

Shut-off Valve
w/Hose Connection

Drain

Vent

9

4. Drain the coil by opening all drain valves and/or the drain plug. Remove the vent plug to

aid the draining process.

5. Close the drain valve(s) and drain plug.

6. Connect the flushing system to the coil. A typical system is shown in Figure 5 - Flushing

System Diagram.

7. With the throttling valve closed, start the pump and operate until the air is vented from

the coil. Next, close the air vent.

8. Open the throttling valve about half-way and circulate the fluid through the coil for 15

minutes. Check the strength of the fluid. A hydrometer or test kit from the fluid manu-
facturer is suitable for this application.

9. Adjust the solution strength as needed and circulate the fluid for another 15 minutes.

10. Repeat steps 8 and 9 until the desired concentration is reached.

11. Shut the pump down and drain the inhibited glycol from the coil.

12. The recaptured fluid can be used to flush other coils.

Note: Be sure to follow the manufactures’ recommendations before utilizing any glycol based anti-

freeze solution. Additional fluid will be required for the pump, connected piping and fluid
reservoir. Formulae are for estimation purposes only.

Figure 5 - Flushing System Diagram